FAT Procedure Template — Full Coverage
Shared by TSIMEREZIVO Team · 4 Oct 2026 · 53 views
# Factory Acceptance Test (FAT) Procedure Template
Project: ______________ System: ______________ FAT No: FAT-____
Location: ______________ Date: ______________ Rev: __
## 1. Purpose
Verify that the control system hardware and software conform to the
functional design specification (FDS) before shipment to site.
## 2. References
- FDS: ______________
- P&IDs: ______________
- I/O Schedule rev: ______________
- Cause & Effect diagrams: ______________
- Panel drawings: ______________
## 3. Attendees
| Name | Role | Company | Signature |
|---|---|---|---|
| | Test lead | | |
| | Client witness | | |
| | Vendor engineer | | |
## 4. Prerequisites — confirm before starting
- [ ] All hardware installed and powered per approved drawings
- [ ] Software build frozen — version recorded: ________
- [ ] Point-to-point wiring checks complete (megger + continuity)
- [ ] Simulation/test equipment calibrated
- [ ] Punch list format agreed
- [ ] Previous FAT punch items closed: N/A or verified
## 5. Hardware verification
- [ ] Physical inspection vs GA drawing (cable entries, labels, IP rating)
- [ ] Power supply voltages within spec at each rail
- [ ] CPU diagnostics clean — no faults logged
- [ ] Redundancy failover: pull primary CPU/network — bump-free transfer
- [ ] I/O card LEDs healthy; channel diagnostics enabled
## 6. I/O channel checks (per I/O schedule)
For EACH channel record: forced/simulated value → system value → PASS/FAIL.
- [ ] Analog inputs: 0% / 25% / 50% / 75% / 100% injection
- [ ] Analog outputs: drive field simulator, measure at terminals
- [ ] Digital inputs: contact open/close, including wetted vs dry
- [ ] Digital outputs: energise/de-energise, measure at load terminals
- [ ] RTD/TC: precision source simulation incl. upscale/downscale burnout
## 7. Functional tests (per FDS / C&E)
- [ ] Every cause & effect row exercised — simulate cause, verify effect
- [ ] Interlocks and permissives proven both directions
- [ ] Sequence logic: step through each phase, verify transitions
- [ ] Alarm setpoints, deadbands, and priorities verified on HMI
- [ ] Trend and historian capture verified
## 8. Communications
- [ ] Each network link broken individually — alarm + failover behaviour
- [ ] Third-party links (Modbus/OPC/Profibus): data integrity spot checks
- [ ] Cybersecurity: unused ports disabled, password policy verified
## 9. Failure modes
- [ ] Power failure → orderly shutdown → restore → recovery
- [ ] Air failure / UPS transfer tested where fitted
- [ ] Watchdog / CPU fault behaviour
## 10. Punch list
| # | Item | Category (A=stop ship / B=site / C=advisory) | Owner | Closed |
|---|---|---|---|---|
| 1 | | | | |
## 11. Sign-off
FAT PASSED / PASSED WITH PUNCH ITEMS / FAILED — circle one.
No Cat-A punch items may remain open at shipment.